Back to graph
energy utility
Tennessee Valley Authority
Federal utility supplying power to xAI Colossus and other TN/MS sites.
Knoxville, TN tva.com
Data centers
12 projects in the dataset
- Meta Huntsville (Project Ferris)· supplies energyHuntsville, Madison, ALOperational
- DC BLOX Huntsville HSV-1· supplies energyHuntsville, Madison, ALOperational2 MW
- xAI Colossus· supplies energyMemphis, Shelby, TNOperational300 MW
- xAI Colossus 2 (Southaven)· supplies energySouthaven, DeSoto, MSOperational500 MW
- xAI Colossus 1 (Memphis)· supplies energyMemphis, Shelby, TNOperational498 MW
- Google Bridgeport Data Center· supplies energyBridgeport, Jackson, ALOperational
- Riot Platforms Paducah· supplies energyPaducah, McCracken, KYOperational35 MW
- Meta Gallatin Data Center· supplies energyGallatin, Sumner, TNOperational
- Meta Huntsville Data Center· supplies energyHuntsville, Limestone, ALOperational
- Riot Platforms Paducah Data Center· supplies energyPaducah, McCracken, KYOperational60 MW
- Google Montgomery County Data Center· supplies energyClarksville, Montgomery, TNOperational
- DC BLOX Chattanooga (CHA1)· supplies energyChattanooga, Hamilton, TNOperational1 MW
Supplies / contracts / lobbies for
Outbound services and contracts
- xAI· supplies
TVA supplies grid power to xAI Colossus.
- Alphabet / Google· supplies
Supplied / contracted / lobbied by
Inbound services and contracts
- Memphis Light, Gas and Water (MLGW)· contracted by
MLGW purchases its bulk electricity supply from TVA, which retains approval rights for power requests above 100MW such as those serving xAI.
- EPB Chattanooga· partners with
EPB is a local power company that distributes TVA-generated power in the Chattanooga area.
Data is editorial seed at this stage; relationships reflect public reporting and filings. Suggestions and corrections via GitHub.