Riverview Innovation and Technology Campus Inc.

Buffalo, NY brownfield redeveloper of the 140-acre former Tonawanda Coke Corp. plant site, planning a 300MW / 500,000 sq ft data center with up to $2B in potential investment.

Buffalo, New York, USA www.riverviewtechcampus.com

Data centers

1 project in the dataset

Supplies / contracts / lobbies for

Outbound services and contracts

  • Honeywell International· partners with

    Honeywell is co-remediating the former Tonawanda Coke site alongside Riverview's developer Jon M. Williams.

Supplied / contracted / lobbied by

Inbound services and contracts

  • Honeywell International· partners with

    Honeywell co-remediates the former Tonawanda Coke brownfield site being redeveloped by Riverview into a 300MW data center campus.