NE Edge LLC
Belmont, Massachusetts-based data center developer co-founded by Thomas Quinn; pursued a ~1.5M sq ft, 300 MW behind-the-meter data center campus at Dominion Energy's Millstone Nuclear Power Station in Waterford, Connecticut. Host fee agreement with Waterford ended in default in 2025.
Data centers
1 project in the dataset
- NE Edge Millstone Data Center Campus· developsWaterford, New London, CTProposed300 MW
Supplies / contracts / lobbies for
Outbound services and contracts
Host Municipality Agreement (since defaulted) committing $231M over 30 years to Waterford in lieu of property taxes for the Millstone-sited data center.
- Dominion Energy· partners with
Proposed behind-the-meter power purchase from Dominion's Millstone Nuclear Power Station to supply 300 MW (~15% of plant output) to the planned data center campus.
Supplied / contracted / lobbied by
Inbound services and contracts
Entered (and later defaulted on) a host-fee agreement valued at $231M over 30 years for the Millstone-sited NE Edge data center.