Back to graph
energy utility

Indiana Michigan Power (AEP)

Investor-owned electric utility subsidiary of American Electric Power serving northern Indiana and southwestern Michigan; expected peak demand to double to 8 GW by 2030 driven by hyperscaler data centers.

Fort Wayne, Indiana, USA$NASDAQ:AEP www.indianamichiganpower.com

Owns / has invested in

Capital and control flowing out

Supplies / contracts / lobbies for

Outbound services and contracts

  • Alphabet / Google· supplies$2.0B

    Supplies Google's $2B Fort Wayne data center and signed demand-response agreement with Google for AI data centers.

  • Microsoft Corporation· supplies$1.0B

    Supplies Microsoft's planned $1B LaPorte, Indiana data center.

  • Amazon / AWS· supplies

    Serves Amazon's $11B+ New Carlisle data center campus and other large-load customers under modified industrial tariff.

Data is editorial seed at this stage; relationships reflect public reporting and filings. Suggestions and corrections via GitHub.