cloud provider
Fluidstack
GPU cloud lessee anchoring Anthropic-backed sites at Lake Mariner NY and Texas; backed by Google.
Owned / funded by
Capital and control flowing in
- Alphabet / Google· invests in
Google has backstopped Fluidstack lease commitments tied to its Anthropic compute investment.
- Next Frontier· joint venture
JV building the 430 MW New Lebanon IN campus.
Data centers
3 projects in the dataset
- Anthropic / Fluidstack at Lake Mariner· operatesBarker, Niagara, NYUnder Construction360 MW
- Hut 8 River Bend AI Campus· operatesSt. Francisville, West Feliciana, LAUnder Construction245 MW
- Coatue / Fluidstack New Lebanon· operatesNew Lebanon, Sullivan, INIn Permitting430 MW
Supplies / contracts / lobbies for
Outbound services and contracts
- TeraWulf· partners with
Fluidstack leases GPU capacity at TeraWulf's Lake Mariner site.
Supplied / contracted / lobbied by
Inbound services and contracts
- Anthropic· partners with
Anthropic's $50B US infrastructure plan anchors with Fluidstack at Lake Mariner NY and Texas.
15-year, $7.0B Fluidstack lease at the River Bend LA campus (245 MW IT; 330 MW utility).
- Alphabet / Google· partners with
Google guarantees Fluidstack's leases — assumes the lease or pays a termination fee if Fluidstack defaults — at New Lebanon and other Fluidstack sites.
Data is editorial seed at this stage; relationships reflect public reporting and filings. Suggestions and corrections via GitHub.