Back to graph
pe firm
DigitalBridge Group
Digital-infrastructure investor; owns/co-owns Vantage, DataBank, Switch.
Owned / funded by
Capital and control flowing in
- Yondr Group· subsidiary of
Acquired by a DigitalBridge-managed investment fund; operates as an independent company within DigitalBridge's portfolio.
DigitalBridge holds majority stake (~55.8%) in Switch following $11B take-private completed Dec 2022.
Owns / has invested in
Capital and control flowing out
- Vantage Data Centers· owns
DigitalBridge is majority owner of Vantage Data Centers.
- DataBank· owns
DigitalBridge is the largest shareholder in DataBank.
DigitalBridge + IFM Investors took Switch private for $11B (2022).
Lead of the $9.2B June 2024 equity raise (upsized from $2.8B); $13B total incremental funding in 2024.
Data centers
23 projects in the dataset
- Vantage TX11 San Antonio· ownsSan Antonio, Bexar, TXOperational32 MW
- Vantage TX21 San Antonio· ownsSan Antonio, Bexar, TXUnder Construction
- Albany, Shackelford, TXUnder Construction1400 MW
- Santa Clara, Santa Clara, CAOperational216 MW
- Vantage Quincy WA Campus· ownsQuincy, Grant, WAOperational89 MW
- Vantage TX22 San Antonio· ownsSan Antonio, Bexar County, TXUnder Construction
- Vantage VA12· ownsSterling, Loudoun County, VAOperational32 MW
- Sterling, Loudoun County, VAUnder Construction96 MW
- Ashburn, Loudoun, VAUnder Construction288 MW
- Port Washington, Ozaukee, WIUnder Construction1000 MW
- Vantage Quincy East· ownsQuincy, Grant, WAAnnounced200 MW
- McCarran, Storey, NVUnder Construction224 MW
- Sparks, Storey, NVUnder Construction224 MW
- Vantage VA4 Centreport· ownsStafford (Centreport Pkwy / I-95), Stafford, VAIn Permitting192 MW
- Vantage Frontier Campus· ownsAbilene, Shackelford County, TXUnder Construction1400 MW
- Red Oak, Ellis County, TXUnder Construction480 MW
- DataBank IAD3· ownsAshburn, Loudoun, VAOperational40 MW
- DataBank IAD1 Ashburn· ownsAshburn, Loudoun, VAOperational9 MW
- Las Vegas, Clark County, NVOperational430 MW
- College Park, Fulton, GAOperational96 MW
- Millersport, Fairfield County, OHApproved800 MW
- Caledonia, Kent, MIOperational320 MW
- Goodyear, Maricopa, AZOperational176 MW
Data is editorial seed at this stage; relationships reflect public reporting and filings. Suggestions and corrections via GitHub.