Crusoe Energy
Operator/developer of the Stargate flagship Abilene campus; raised >$1B from Founders Fund, Fidelity.
Owned / funded by
Capital and control flowing in
Lead financier of Crusoe's $11.6B debt+equity raise for the Stargate Abilene Phase 2 campus.
Mubadala participant in the Dec 2024 Crusoe $600M Series D (Founders Fund lead).
~$7B committed to BFC Power + Cheyenne Power Hub gas generation for Project Jade.
Data centers
2 projects in the dataset
- Stargate Abilene Campus· developsAbilene, Taylor, TXOperational1200 MW
- Project Jade (Crusoe + Tallgrass)· developssouth of Cheyenne (Terry Ranch Rd corridor), Laramie, WYApproved1800 MW
Supplies / contracts / lobbies for
Outbound services and contracts
- The Stargate Project· partners with
Crusoe is the developer/operator of the Stargate flagship Abilene TX campus.
Supplied / contracted / lobbied by
Inbound services and contracts
- Bechtel Corporation· contracted by
Bechtel is the EPC contractor for Stargate Abilene.
- VoltaGrid· partners with
VoltaGrid operates the on-site natural-gas microgrid (~700 MW, 210 gensets) at Stargate Abilene.
- Lancium· partners with
Lancium owns the land + electrical infrastructure at the Crusoe Stargate Abilene campus.