developer
CoreSite
Carrier-neutral colocation operator; wholly-owned by American Tower. DE3 Denver active in 2026 community-permit dispute.
Owned / funded by
Capital and control flowing in
American Tower acquired CoreSite in 2021 for $10.1B.
Data centers
11 projects in the dataset
- CoreSite DE3 Denver· operatesDenver (Elyria-Swansea), Denver, COUnder Construction60 MW
- CoreSite SV9· operatesSanta Clara, Santa Clara, CAOperational34 MW
- CoreSite DE2· operatesDenver, Denver, COOperational
- CoreSite DE1· operatesDenver, Denver, COOperational
- Santa Clara, Santa Clara, CAApproved72 MW
- CoreSite AT1 Atlanta· operatesAtlanta, Fulton County, GAOperational10 MW
- Reston, Fairfax, VAApproved
- Raleigh, Wake, NCOperational4 MW
- CoreSite DE3· developsElyria-Swansea (Denver), Denver County, COUnder Construction75 MW
- CoreSite Reston Campus (VA1/VA2/VA3)· operatesReston, Fairfax, VAOperational
- CoreSite AT2· operatesMarietta, Cobb, GAOperational2 MW