City of Lansing
Capital city of Michigan whose City Council and Planning Commission reviewed Deep Green's proposed $120M, 24MW downtown data center project in partnership with Lansing BWL; Deep Green withdrew its rezoning application in April 2026 amid community pushback over transparency and contract terms.
Lansing, Michigan, USA www.lansingmi.gov
Data centers
1 project in the dataset
- Lansing, Ingham, MIApproved24 MW
Supplied / contracted / lobbied by
Inbound services and contracts
- Deep Green· partners with
Sought zoning amendment from City of Lansing to enable proposed 24MW heat-reuse data center on 2.7-acre vacant parking lot at Cedar/Kalamazoo Streets in the Stadium District; application withdrawn April 2026.