Atlas Development
Land assemblage / rezoning developer that originated the Project Sail Coweta GA site for Prologis.
Owns / has invested in
Capital and control flowing out
Atlas Development partnered with Prologis on Project Sail (Coweta County, GA); Prologis set to acquire the 831-acre, ~$17B site.
Data centers
9 projects in the dataset
- Avemore Data Park· developsVilla Rica, Carroll, GAProposed
- Project Sail· joint ventureNewnan, Coweta, GAApproved900 MW
- Atlas Battey Data Center Campus· developsRome, Floyd County, GAProposed
- Project Sail (Prologis / Atlas)· developsnear Newnan, Coweta, GAApproved900 MW
- Dixon Data Center (Project Springbank)· developsAdairsville, Bartow, GACancelled200 MW
- Project Sassy Data Center Campus· developsRome, Floyd, GAProposed504 MW
- Atlas Power Williston Data Center· developsWilliston, Williams, NDOperational700 MW
- Project Gracie Data Center Campus· developsRome, Floyd, GAProposed
- Avemore Data Park· developsVilla Rica, Carroll County, GAApproved
Supplied / contracted / lobbied by
Inbound services and contracts
- Prologis· partners with
Prologis under contract to take the 832-acre Coweta GA site originated by Atlas Development.
- GeorgiaLink Public Affairs Group· lobbies for
Arthur Edge IV of GeorgiaLink represented Atlas Development on Project Sail at zoning.
Signed $5.7M term sheet to sell 100-acre Battey Business Complex to Atlas Development for a data center project
Coweta County Commissioners voted 3-2 to approve rezoning for Atlas Development's 'Project Sail' 832-acre, 4.34M sq ft data center campus.
Reviewing Atlas Development data center projects projected to bring up to $50M in annual tax revenue to county.
Rome Floyd Development Authority signed a $5.7M land deal with Atlas Development for the 100-acre 'Project Gracie' (2.4M sq ft data center campus) at Battey Business Complex.